TLE 6 Industrial Arts Module 6: Constructing a Project Plan

Grade 6 TLE Industrial Arts Module 6 on constructing a project plan, managing time, money, materials and effort, and rating projects with rubrics.

This is the Technology and Livelihood Education (TLE) Grade 6 Industrial Arts Module 6, “Constructing A Project Plan,” a self-learning module made for home-based learning through the Alternative Delivery Mode. It was written for Grade 6 learners and was developed by DepEd Region VI-Western Visayas. After the module, learners should be able to write a complete project plan, manage their time, money, materials, and effort wisely, and rate a finished project using a rubric.

On this page 8 sections

What learners will learn

At the end of the module, learners should be able to:

  • Construct a project plan (TLE6IA-0d-6)
  • Consider deliberate policies on sustainable development in constructing the project plan
  • Demonstrate resourcefulness and management skills in the use of time, materials, money, and effort
  • Assess the quality of an enhanced product using rubrics
  • Refine a product based on the assessment made

Lessons in this module

  1. Policies on sustainable development in constructing the project plan. Learners find out what a project plan is, learn its seven parts, study a sample plan for an extension cord, and write their own plan.
  2. Resourcefulness and management skills in the use of time, materials, money, and effort. Learners see what it means to be resourceful and how to manage the four elements of a project.
  3. Assessing product using rubrics. Learners learn what a rubric is, why it matters, its three parts, and how to use one to rate a project.

Key ideas: the project plan

The module defines a project plan as a formal document that guides the execution of a project. It should be prepared before starting, because it helps you organize your ideas and save time, money, and effort. A project plan has these parts:

PartWhat it tells
Project ProponentThe owner of the project
Project TitleWhat the project is all about
Project ObjectivesThe purpose of the project
Working DrawingA scale drawing of the object or structure, for direct use by the workman
Bill of MaterialsThe quantity, unit, description, unit price, and total cost of every item
Tools NeededThe carpentry or industrial tools, machines, or gadgets needed
ProcedureThe exact steps in making the project

The module’s sample plan is an extension cord by Juan Dela Cruz. Its bill of materials lists one convenience outlet (P40.00), one male plug (P38.00), and five meters of #16 electrical wire at P15.00 per meter (P75.00), for a total of P153.00. The tools needed are pliers, screwdrivers, and a wire stripper. The procedure has 11 steps, from preparing tools and stripping the wire by two centimeters to connecting the wires to the plug and outlet and replacing the covers so no wire is exposed.

The lesson opens with a story about Andy, a Grade 6 learner who wants to make a feather duster from recycled materials. His teacher, Mr. Jose, tells him to prepare a project plan first.

Key ideas: resourcefulness and management

A resourceful person gets the most out of few resources and finds effective, efficient, and creative ways of doing things. The module explains four elements to manage:

  • Time: organizing and planning the time spent on activities. It includes effective planning, setting goals and deadlines, delegating, prioritizing, and spending the right time on the right activity. Poor time management delays a project.
  • Money: one of the most important things in a project; manage it wisely to avoid waste.
  • Effort: the action you put in to reach your goal, including physical strength. Following the plan closely helps you avoid errors and repeated work.
  • Materials: the supplies, equipment, tools, and other physical resources the project needs.

The module uses the story of Randy, who wants to save for new shoes but struggles to manage his time between chores, homework, and helping Aling Mameng make kakanin.

Key ideas: rubrics

A rubric is a guide that states what is expected in an assignment or project and helps evaluate learners’ work. It helps learners, parents, and teachers see what quality work looks like, and it helps teachers explain grades. The module stresses that learners should receive the rubric before they start, so they know how they will be rated. A rubric has three parts:

  1. Performance criteria: the key elements of the work or product
  2. Rating scale: the levels of performance
  3. Indicators: concrete descriptions of each level

The sample rubric rates a project on Workmanship and Creativity, Materials Used, and Procedure, with scores of Excellent (5), Good (3), and Fair (1). For example, a project using 100% locally available or indigenous materials earns 5, while 75% earns 3 and 50% earns 1.

How to use this module

  • Learners: Read each lesson in order: What’s In, What’s New, What is It, What’s More, What I Have Learned, What I Can Do, Assessment, and Additional Activities. Write all answers on a separate sheet of paper and do not mark the module. Check your work with the answer key at the end honestly.
  • Parents: Help your child find materials at home for the project plan activities, and review the rubric together so you both know what a good output looks like.
  • Teachers: The What I Can Do and Additional Activities tasks have open answers that you need to check, including the learner’s own project plan rated by the module’s rubric on completeness of parts and content.

Frequently asked questions

What grade is this TLE Industrial Arts module for?

It is for Grade 6 learners. It is Module 6 of TLE Industrial Arts and was produced by DepEd Region VI-Western Visayas.

What are the parts of a project plan?

The module lists seven parts: Project Proponent, Project Title, Project Objectives, Working Drawing, Bill of Materials, Tools Needed, and Procedure.

Does the module have an answer key?

Yes. An answer key for all three lessons is at the end of the module. Open-ended tasks such as writing your own project plan are checked by the teacher.

What is a rubric?

A rubric is a guide that states what is expected in a project and helps evaluate the work. It has three parts: performance criteria, rating scale, and indicators.

What does the Bill of Materials contain?

It contains the quantity, unit, description, unit price, and total cost of every item needed for the project.

Full text of the module

The text below is a transcription of the PDF above, as printed.

Technology and Livelihood Education

Industrial Arts – Module 6: Constructing A Project Plan

[illustration: students studying under a tree, at a desk with a globe, and a boy writing by a lamp]

CO_TLE-IA6_ Module 6

TLE – Grade 6 Alternative Delivery Mode Industrial Arts – Module 6: Constructing A Project Plan First Edition, 2019

Republic Act 8293, section 176 states that: No copyright shall subsist in any work of the Government of the Philippines. However, prior approval of the government agency or office wherein the work is created shall be necessary for exploitation of such work for profit. Such agency or office may, among other things, impose as a condition the payment of royalties.

Borrowed materials (i.e., songs, stories, poems, pictures, photos, brand names, trademarks, etc.) included in this module are owned by their respective copyright holders. Every effort has been exerted to locate and seek permission to use these materials from their respective copyright owners. The publisher and authors do not represent nor claim ownership over them.

Published by the Department of Education Secretary: Leonor Magtolis Briones Undersecretary: Diosdado M. San Antonio

Development Team of the Module

Writer: Teofilo M. Villanueva II

Editors and Reviewers: Jeanalyn L. Jamison, Ana Lee C. Bartolo, Petronilo R. Bartolo, Velly P. Seguisa

Illustrator: Jofel D. Nolasco

Layout Artist: Jofel D. Nolasco, Ana Lee C. Bartolo, Jecson L. Oafallas

Management Team: Ramir B. Uytico, Pedro T. Escobarte, Jr., Neri Anne M. Alibuyog, Bernie L. Libo-on, Elena Gonzaga, Donald T. Genine, Melgar B. Coronel, Ana Lee C. Bartolo, Jeanalyn L. Jamison

Printed in the Philippines by ________________________

Department of Education – Region VI-Western Visayas Office Address: Duran Street, Iloilo City, Philippines, 5000 Telefax: (033) 336-2816, (033) 509-7653 E-mail Address: deped6@deped.gov.ph

6

Technology and Livelihood Education

Industrial Arts – Module 6: Constructing A Project Plan

Introductory Message

This Self-Learning Module (SLM) is prepared so that you, our dear learners, can continue your studies and learn while at home. Activities, questions, directions, exercises, and discussions are carefully stated for you to understand each lesson.

Each SLM is composed of different parts. Each part shall guide you step-by-step as you discover and understand the lesson prepared for you.

Pre-tests are provided to measure your prior knowledge on lessons in each SLM. This will tell you if you need to proceed on completing this module or if you need to ask your facilitator or your teacher’s assistance for better understanding of the lesson. At the end of each module, you need to answer the post-test to self-check your learning. Answer keys are provided for each activity and test. We trust that you will be honest in using these.

In addition to the material in the main text, Notes to the Teacher are also provided to our facilitators and parents for strategies and reminders on how they can best help you on your home-based learning.

Please use this module with care. Do not put unnecessary marks on any part of this SLM. Use a separate sheet of paper in answering the exercises and tests. And read the instructions carefully before performing each task.

If you have any questions in using this SLM or any difficulty in answering the tasks in this module, do not hesitate to consult your teacher or facilitator.

Thank you.

What I Need to Know

This module was designed and written with you in mind. It is here to help you to construct project plan. The scope of this module permits it to be used in many different learning situations. The language used recognizes the diverse vocabulary level of students. The lessons are arranged to follow the standard sequence of the course. But the order in which you read them can be changed to correspond with the learning materials you are now using.

The module is divided into three lessons, namely:

a. Policies on sustainable development in constructing the project plan

b. Resourcefulness and Management skills in the use of time, materials, money and effort

c. Assessing the quality of enhanced products using rubrics

At the end of this module, you should be able to:

a. Construct project plan; (TLE6IA-0d-6)

b. Consider deliberate policies on sustainable development in constructing the project plan;

c. Demonstrate resourcefulness and management skills in the use of time, materials, money, and effort;

d. Assess the quality of enhanced product using rubrics; and

e. Refine product based on assessment made.

What I Know

Why is there a need for a project plan before we build our houses, bridges or even school buildings? Simple project in school?

What is the importance of a project plan?

In planning for a project and getting it materialized, one must know how to be resourceful in the preparation and accomplishment of a project plan. It is important to properly manage the different elements that we can associate in preparation and of a workable project.

Lesson 1: Policies on sustainable development in constructing project plan

Why do we need to construct a project plan? Project planning is essential in making and implementing a project that we desire. Starting a project requires careful planning on what to prepare, on how to do it and what to do with the finished product. It enables you to organize your ideas, save time, money and effort.

What’s In

Directions: Which of the following project needs a plan? Put a CHECK (✓) before the number if it requires a project plan and CROSS (X) if doesn’t require the plan. Write your answer on a separate sheet of paper.

_____ 1. Building a house

_____ 2. Cutting a plain sheet

_____ 3. Constructing a table

_____ 4. Making Dustpan

_____ 5. Making artwork

_____ 6. Connecting wires

_____ 7. Preparing tools and materials

_____ 8. Making card for parents

_____ 9. cutting of lumber

_____ 10. Applying varnish

What’s New

Andy a Grade 6 learner, wanted to make a “Feather Duster” from recycled materials, the project he planned to develop in his EPP class but was not materialized due to the early closure of his school because of COVID -19 pandemic and he had to stay at home. He would like to start this project, so, he contacted his teacher Mr. Jose online, to get advice on what he will do to be able to start his project.

Mr. Jose was very happy hearing such eagerness of Andy in coming out with an EPP project. So, he instructed Andy to prepare first a project plan that will guide him throughout the development of the project. Mr. Jose patiently discussed the parts of the Project Plan. After, three days of meeting online, Andy is now ready to start his dream project.

Mr. Jose also assured Andy that he will be available anytime via online when he needs some help.

Why is project plan important according to Mr. Jose?

What is a project Plan? What are its parts?

What is It

A Project plan is a formal document designed to guide in the execution of a project. It must be prepared before starting because it serves as the key to a successful project.

Parts of a Project Plan

A. Project Proponent – indicates the owner of the project

B. Project Title – tells what the project is all about

C. Project Objectives – tell the purpose of the project

D. Working Drawing – shows the scale drawing of an object to be made or structure to be built intended for direct use by the workman.

E. Bill of Materials – tell the materials to be used. This part contains the unit, quantity, description, the unit price and the total cost for every item needed.

F. Tools Needed: tells the different carpentry or industrial tools, machines or gadgets needed in making the project

G. Procedure: tells the exact steps in the preparation of the project. This will serve as the guide in project making.

Sample Project Plan:

A. Project Proponent: Juan Dela Cruz

B. Project Title: Extension Cord

C. Project Objectives:

  1. To be able to make extension cord.
  2. To create a simple project according to prepared plan.

D. Working Drawing:

[illustration: extension cord with a convenience outlet and a male plug]

Jofel D. Nolasco, Extension Cord, 2019

E. Bill of Materials:

QuantityUnitDescriptionUnit PriceTotal Cost
1pieceConvenience outletP 40.00P40.00
1pieceMale plugP 38.00P 38.00
5meterElectrical wire # 16P 15.00P 75.00
TotalP 153.00

All Illustrations on this page were made by Jofel D. Nolasco

F. Tools Needed

[illustration: pliers, screwdrivers, and wire stripper]

Pliers Screwdrivers Wire Stripper

G. Procedure:

  1. Prepare all materials and tools needed for the project.
  2. Measure the parts of the wire to be peeled or stripped.
  3. Peel off the skin by two centimeters.
  4. Loosen the screw of the male plug.
  5. Insert the wire into the male plug.
  6. Twist both ends of the wire to keep the wires from making contact with each other.
  7. Put the cover of the plug so the wire will not be exposed and cause electric shock.
  8. Split the cord wires at the other end about 4 cm long, then follow procedure no. 3
  9. Connect the wires to the connectors.
  10. Open the convenience outlet then remove the screw.
  11. Insert the wire connectors to the screws, tighten it and return the cover.
What’s More

A. Directions: Fill in the blanks with appropriate parts of the project plan listed Inside the box below. Write your answer on a separate sheet of paper.

Project Title Working Drawing Tools Needed Project Objectives Project Proponent Procedure Bill of Materials

_____________ 1. shows the scale of an object to be made or structure to be built intended for direct use by the workman

_____________ 2. tells the different carpentry or industrial tools, machines or gadgets needed in making the project

_____________ 3. indicates the owner of the project

_____________ 4. tell the purpose/s of the project

_____________ 5. tells the exact steps in the preparation of the project. This will serve as the guide in project making.

What I Have Learned

Directions: Fill in the blanks with the correct answer or term found inside the box. Write your answer on a separate sheet of paper.

quantity objective money procedure tools

In making a Project Plan. The first thing you have to consider is to have your _____ (1) _____ where you will determine the purpose of the project. The List of Materials contains the _____ (2) _____, unit, and description of materials. The _____ (3) _____ will serve as your guide in making your project. _____ (4) _____ is also important in purchasing your material and other expenses. Following the plan and using appropriate _____ (5) _____ will give you not only quality output of the project but also keep you safe from any accident.

What I Can Do

Project Plan is an essential document design to guide project developer in starting a sustainable project. It is necessary before undertaking any project because it serves as guide in accomplishing the project. It gives the project implementer an idea on what needs to be done, how much to spend and what procedures to undertake.

Directions: Using the parts below construct your own project plan. Write it on a separate sheet of paper.

A. Project Proponent: _____________

B. Project Title: _____________

C. Project objectives: _____________

D. Working Drawing: _____________

E. Bill of Materials: _____________

F. Tools Needed: _____________

G. Procedure: _____________

Assessment

A. Directions: Read and answer each question. Write the letter of your answer in a separate sheet of paper.

  1. What do you call a document designed to guide you in the execution of a project

    • A. Building Plan
    • B. Action Plan
    • C. Project Plan
    • D. Project Proponent
  2. Which part of the project plan contains the quantity of the materials to be used?

    • A. Working Drawing
    • B. Tools Needed
    • C. Procedure
    • D. Bill of Materials
  3. It shows you the purpose of the plan.

    • A. Project Proponent
    • B. Procedure
    • C. Objective
    • D. Materials
  4. Scissors, glue gun, pliers and cutter are examples of ____________________.

    • A. Materials
    • B. Tools
    • C. Furniture
    • D. Machine
  5. The illustration of the structure to be built or made can be found in ____________.

    • A. Procedure
    • B. List of Tools
    • C. Bill of Materials
    • D. Working Drawing

B. Directions: Match column A with Column B. Write the letter of the correct answer in your answer sheet.

AB
1. Tells the exact steps in the preparation of the project.A. Project Objectives
2. Indicates the owner of the projectB. Bill of Materials
3. Shows the scale of an object to be made or structure to be builtC. Procedure
4. Tells the purpose of the projectD. Working Drawing
5. It contains the unit, quantity, description, the unit price and the total cost for every item neededE. Project Proponent
Additional Activities

Directions: Create a simple project plan and observe the format below.

Project Plan

a. Project Proponent: b. Project Title: c. Project Objectives: d. Working Drawing: e. Bill of Materials:

QuantityUnitDescriptionUnit PriceTotal Cost

f. Materials Needed: g. Procedure:

Rubrics used in rating the project plan.

Performance CriteriaExcellent 5Good 3Fair 1Score
Completeness of Parts6 Parts of the Project plan were used4-5 Parts of the Project plan were used3 and below parts of the Project Plan were used
ContentThe content of each part of the project plan is complete.The content of each part of the project plan lack 1-2 needed information or dataThe content of each part of the project plan lack 3-5 needed information or data
Total

Lesson 2 – Resourcefulness and Management skills in the use of Time, Materials, Money, and Effort

Resourcefulness, effective and efficient management of the following elements are also considered in the preparation of a project, based on prepared plan: Time, Materials, Money and Effort.

What’s In

Directions: Write Yes in your answer sheet if the following situation is essential in the preparation a project plan and No if not.

_____________ 1. The amount to be used in the preparation of the project should be given consideration.

_____________ 2. Prepare workable and attainable target.

_____________ 3. The kind and quality of materials need to be check before the start of a project.

_____________ 4. The bill of materials contains the unit, quantity and procedure in the preparation of the project

_____________ 5. A project plan is needed only in project costing ten thousand pesos or more.

What’s New

Randy a Grade 6 learner of San Miguel Elementary School wanted to buy a new pair of shoes. He promised himself that he will not ask money from his Tatay and Nanay he wanted to have it through his savings. During class days, he sees to it that he would have save some of his baon. And on weekends, after doing his household chores, he thought of helping Aling Mameng in making kakanin to have extra income.

Weeks past, but Randy was not able to do his plan, he had a hard time managing his time doing his task at home, his homework and helping Aling Mameng.

What do you think is the problem of Randy?

Will he be able to manage his time? How?

What is It

Accomplishing task, activities or project need thorough planning and preparations. One would be able to achieve his or her goal, if he or she is resourceful enough in managing the time, money, materials and even the effort.

A resourceful person can achieve maximal results from minimal resources. Wise utilization of available resources on hand to implement a propose project. Being resourceful means one can find effective and efficient ways of doing things; they tend to be innovative and imaginative. Resourcefulness is the ability to find a way to achieve your goal or to make one.

Resourcefulness and Management skills in the use of the following:

  1. Time – Time management is essentially the ability to organize and plan the time spent on activities in a day. It increases effectiveness and productivity. It is a key aspect of project management and involves skills such as planning, setting goals and prioritizing for a better performance.

Time is an important element in the accomplishment of a project. Poor management of time will result to delayed accomplishment of project or task. Manage your time effectively and you will achieve your goals successfully.

Time Management includes:

  1. Effective Planning
  2. Setting goals and objectives
  3. Setting deadlines
  4. Delegation of responsibilities
  5. Prioritizing activities as per their importance
  6. Spending the right time on the right activity

Effective time management allows individuals to assign specific time slots to activities as per their importance.

  1. Money – One of the most important thing in the accomplishment of a project or plan. Managing money or finances well will result to a better project implementation thus, make sure that is managed wisely to avoid wastage of materials.


  2. Effort – The result of an action to achieve your goal. You must be persistent in pursuing your goal and achieving your desired project. Investing energy also sometimes means investing physical strength to do something. Follow strictly what is written in the plan to go away of errors and repetitions.


  3. Materials – The supplies that you will need in making your project. Materials may include apparatus, equipment, tools, gears, machinery and other physical resources that are necessary for completing the different processes in project management.


What’s More

Directions: Read the situations below. Tell whether it tells about wise use of Time, Money, Materials or Effort. Write your answer on a separate sheet of paper.

  1. _____ Mr. Cruz always consider the amount she will be using in the preparation of his project.


  2. _____ Nancy always prepares delicious and nutritious merienda for her younger siblings. She uses her strength to make them happy and satisfied.


  3. _____ Mang Adong always arrive fifteen minutes before the scheduled meeting.


  4. _____ Lando check the kind and the quality of wood he will be using in the construction of their side table.


  5. _____ Linda always prepare her daily plan of activities ahead. This serves as her daily guide.


What I Have Learned

Directions: Fill in the blank with the appropriate word or terms from the box below. Write your answer on a separate sheet of paper.

MoneyTimeMaterials
EffortResourcefulnessResourceful
  1. A ____________ person can find effective and efficient ways of doing things; they tend to be innovative and imaginative can achieve
  2. ____________ is the ability to find a way to achieve your goal or to make one.
  3. ____________ the most important thing in purchasing materials in the accomplishment of a project or plan.
  4. ____________ include apparatus, equipment, tools, gears, machinery and other physical resources that are necessary for completing the different processes in project.
  5. _______________ is the result of an action to achieve your goal.
What I Can Do

The Grade 6 learners of Mr. Ramos planned to make souvenir items to be sold during the city “Pasalamat Festival” as their income generating project.

If you were one of Mr. Ramos learner, what are you going to consider in the preparation of their project as a resourceful learner in terms of?

  1. Time Management – ___________________________________________
  2. Money – _______________________________________________________
  3. Materials – ____________________________________________________
  4. Effort – ________________________________________________________

Assessment

I. Directions: Match column A with the simple description of terms found in column B. Write the letter of correct answer on your answer sheet.

AB
1. MoneyA. supplies that you will need in making your project
2. EffortB. effective, efficient and innovative ways of doing things
3. ResourcefulnessC. It means investing physical strength to do something
4. MaterialsD. It should be managed wisely to avoid wastage or additional budget.
5. TimeE. It is a key aspect of project management and involves skills such as planning, setting goals and prioritizing for a better performance

II. Directions: Read the situations below. Tell whether it tells about management of Time, Money, Materials or Effort. Write your answer on a separate sheet of paper.

  1. Using resources that are available in the locality in the preparation of a project.
  2. Simeon sees to it that he is in the right condition before starting his work, he is 100 percent ready and is prepared.
  3. Observing the allocated number of days in accomplishing of a plan or a project.
  4. Checking the prices of the resources to be used that is durable but within allocated budget.
  5. Observance of the objectives and activities in the planned task.

III. Directions: Tell what each situation demonstrates. Write in your answer sheet E – if it demonstrates effort, M for money, MM for management of materials, T for time and R for being resourceful.

________1. Keeping a journal and making a list of what needs to be accomplished for a day, a week or a month.

________2. Carlo buys cheap but durable materials for his project.

________3. Linda and Lowela check and compare all prices of the materials that they will use in their project before buying their needed materials.

________4. Allan’s group use the skills they’ve learn in their EPP class in making the project.

________5. Reno check available materials that can still be used to lessen the amount in purchasing materials.

Additional Activities

List down the different activities or steps in the preparation of your previous project plan. Check whether you are managing your Time, money, materials and effort efficiently and effectively. Write your answer on your answer sheet.

  1. Time ______________________________________________________

  2. Money _______________________________________________________

  3. Materials ______________________________________________________

  4. Effort – ______________________________________________________

Lesson 3 Assessing Product Using Rubrics

The preparation of a product is a long way process. One must be resourceful enough in the choice of his materials to be used and he/or she must have a concrete plan in order to make it successful.

What’s In

Directions: Write True if the statement is right and False if it is wrong. Write your answer on a separate sheet of paper.

  1. _____ Assessing a project plan will include list of workable criteria.
  2. _____ Time is an important factor in the preparation and accomplishment of a plan.
  3. _____ Any kind of materials can be used in making a project.
  4. _____ Score or rating is essential in the final decision if the project passed or failed.
  5. _____ Checking current prices of materials can be of help in selecting low cost but durable resources.
  6. _____ Rubric is an essential tool in assessing a finish project.
  7. _____ Performance in the rubric will tell the learners his or her score in the preparation of the output
  8. _____ Parents and learners will not be guided on how their output will be rated using rubrics.
  9. _____ There are at least 3 indicators in a rubric.
  10. _____ Rubrics should not be shared or provided to the learners before doing their output, it should be given during the rating of the output or project.
What’s New

Teacher Carlos wanted to give fair and just grades to all his Grade 6 learners in the submission of their EPP output. He informed them that they will have 1 project output per grading period for a total of 4 for the whole school year.

What should teacher Carlos’ basis in giving grades or rating to his individual learners’ output. When should teacher Carlos give the rubric/s to the learners so that that they will be guided in the preparation of their project?

What is It

In assessing learners’ output or project, an assessment tool called Rubrics is very essential in checking the quality of the output or project, including the preparation of a workable and attainable project plan.

What is a rubric?

Rubric is a “guide” that states what is expected in an assignment or project and helps to evaluate the learners’ performance.

It is also a tool used to measure learners’ work, a working guide for learners and teachers.

What is the importance of a Rubric?

Rubrics help learners, parents and teachers identify what quality work is. Learners can judge their own work and accept more responsibility of the final product.

Rubrics help the teacher to easily explain to the learners why they got the grade that they received. Parents who work with their children also have a clear understanding of what is expected for a project.

Why use Rubrics?

Rubrics improve learners end products and help increase learning. When learners received rubrics beforehand, they understand what is expected and how they will be evaluated, and they can prepare accordingly.

What are the parts of a rubric?

Rubric is a scoring guide use to evaluate performance, a product, or a project. It has three parts.

  1. Performance criteria – describe the key elements of the learners’ work or product.
  2. Rating scale – identifies levels of performance
  3. Indicators – provide examples or concrete descriptors of the level of performance. This could be found under each sections of the rating scales.

Example of a rubric in assessing Project

Performance CriteriaExcellent 5Good 3Fair 1Score
Workmanship & CreativityThe material is properly put together and neatly done.The materials are put together but not so neatly done.Some of the materials are not properly put together and not neatly done
Materials UsedUses 100% locally available/ indigenous materials.Uses 75% locally available/ indigenous materialsUses 50% locally available/ indigenous materials
ProcedureFollowed procedure correctly.One-two steps was not applied correctlyThree or more steps not applied correctly
Total

[transcriber’s note: in the original, “Total” is printed centered across the first three columns of the last row]

What’s More
Activity 1: Understanding the terms learned

Directions: Match the terms in column A with the appropriate meaning or description found in Column B. Write your answer in a separate sheet of paper.

AB
___1. Rubricsa. Identifies levels of performance
___2. Indicatorb. Describes the key elements of the learners work or product.
___3. Performance Criteriac. A tool used to measure learners work, a working guide for learners and teachers.
___4. Rating Scaled. The process of checking or evaluating quality of the product
___5. Assessmente. Concrete descriptors of the level of performance. This could be found under each sections of the rating scales.
Activity 2: Identification of the elements of rubrics

Directions: Read each statement below and Write I if it tells about the Importance of a rubric, U for uses of Rubrics and P for parts of a rubric. Write it in your answer sheets.

  1. Rubrics improve learners end products and help increase learning.
  2. Performance criteria describe the key elements of the learners’ work or product.
  3. Rubrics help learners, parents and teachers identify what quality work is.
  4. Rubrics help the teacher to easily explain to the learners why they got the grade that they received.
  5. Learners will understand what is expected and how they will be evaluated.

What I Have Learned

Directions: Fill in the blanks with the word or words from the list below that will make the statement correct. Write your answer on a separate sheet of paper.

rubric | rating scale | explain | descriptors | performance

  1. _____ are criteria that describe the key element of the learners work or product
  2. _____ is a guide or an assessment tool that states what is expected in an assignment or a project.
  3. To identify the level of performance _____ is provided.
  4. Indicators provide concrete _____ of the level of performance of each learner.
  5. Rubric helps teachers to clearly _____ to the learners how they are rated in their output or project.

What I Can Do

Directions: Read the situation below and answer the questions that follows. Write your answer on a separate sheet of paper.

The Grade 6 learners of Mr. Ortega will make a project in their EPP class. He emphasizes the use of cost efficient and locally available materials in the preparation of their project. Peter searched for available materials in their home. He used indigenous and recyclable materials as part of the material for his EPP project.

  1. What kind of a learner is Peter?
  2. Is he right in doing such thing? Why or why not?
  3. How do you value your time, money, effort and material in making your project and for the accomplishment of your plan?

Assessment

I. Directions: Read and answer the test below. Write the letter of the correct answer on a separate sheet of paper.

  1. What tool is used to guide learners in improving their project.

    • a. Rubrics
    • b. Evaluation form
    • c. Assessment
    • d. indicators
  2. What part of the rubric identifies learners level of performance?

    • a. Performance
    • b. Indicators
    • c. Rating Scale
    • d. Tool
  3. What will you do to get a rating of 5, as the highest in an output that used indigenous materials?

    • a. Use 75% indigenous material in making the project.
    • b. Use 50% indigenous materials in making the project.
    • c. Use 100% indigenous materials in making the project.
    • d. Use 100% imported materials in making the project
  4. What will be your rating in workmanship, when your project was properly and neatly done?

    • a. 5 or excellent
    • b. 3 or good
    • c. 1 or fair
    • d. no score
  5. What part of the rubric provides example and concrete descriptions of the level of performance in the preparation of the output?

    • a. Performance criteria
    • b. Rating scale
    • c. indicators
    • d. Score

II. Directions: Write Yes if the statement tells importance and uses of rubric and No if not. Write it on your answer sheet.

  1. Rubrics help the teachers evaluate and give accurate ratings to the learners.
  2. Parents have a clear understanding of what is expected of their children’s project.
  3. A Rubric is a tool in acquiring mastery of the lesson.
  4. Rubrics can only be used by teachers and not the learners.
  5. A Rubric is used to measure learners work, a working guide for learners and teachers.

Additional Activities

Look for a previous project you submitted to your teacher. Using the rubrics below assess your project and give your rating.

Performance CriteriaExcellent 5Good 3Fair 1Score
Workmanship & CreativityThe material is properly put together and neatly done.The materials are put together but not so neatly done.Some of the materials are not properly put together and not neatly done
Materials UsedUses 100% locally available/ indigenous materials.Uses 75% locally available/ indigenous materialsUses 50% locally available/ indigenous materials
ProcedureFollowed procedure correctly.One-two steps was not applied correctlyThree or more steps not applied correctly
Total

Answer Key

[transcriber’s note: this page is printed upside down; it is transcribed here in reading order, with the lesson columns in sequence]

Lesson 1

What’s In
  1. /
  2. X
  3. /
  4. /
  5. X
  6. /
  7. X
  8. X
  9. X
  10. X
What’s More
  1. Working Drawing
  2. Tools Needed
  3. Project Proponent
  4. Project Objective
  5. Procedure
What I Have Learned
  1. objective
  2. quantity
  3. procedure
  4. money
  5. tools
What I Can Do

Answer may vary

Teacher will check the answer

Assessment

A.

  1. C
  2. D
  3. C
  4. B
  5. D

B.

  1. C
  2. E
  3. D
  4. A
  5. B
Additional Activities

Answer may vary

Lesson 2

What’s In
  1. Yes
  2. Yes
  3. Yes
  4. No
  5. No
What’s More
  1. Money
  2. Effort
  3. Time
  4. Material
  5. Time
What I Have Learned
  1. Resourceful
  2. Resourcefulness
  3. Money
  4. Material
  5. Effort
What I can Do

Answer may vary

Assessment
IIIIII
1. D1. Material1. T
2. C2. Effort2. MM
3. B3. Time3. M
4. A4. Money4. E
5. E5. Time5. R
Additional Activities

Answer may vary teacher will check learners’ responses

Lesson 3

What’s In
  1. True
  2. True
  3. False
  4. True
  5. True
  6. True
  7. True
  8. False
  9. True
  10. False
What’s More
Activity 1
  1. C
  2. E
  3. B
  4. A
  5. D
Activity 2
  1. I
  2. P
  3. U
  4. U
  5. I
What I Have Learned
  1. Performance
  2. Rubric
  3. descriptors
  4. rating scale
  5. explain
What I Can Do

Answer may vary

Assessment
III
1. A1. Yes
2. C2. Yes
3. C3. Yes
4. A4. No
5. C5. Yes
Additional Activities

Answer may vary

References

Department of Education Curriculum Guide 2016, EPP 6, Industrial Arts pages 38 – 41

Department of Education MELCs in EPP/TLE Grade 6 Industrial Arts pages 353 – 354

Websites:

www.technopedia.com> definition> project-plan

youtube.com/watch?v=WUC_a0WJY9o

For inquiries or feedback, please write or call:

Department of Education – Bureau of Learning Resources (DepEd-BLR)

Ground Floor, Bonifacio Bldg., DepEd Complex Meralco Avenue, Pasig City, Philippines 1600

Telefax: (632) 8634-1072; 8634-1054; 8631-4985

Email Address: blr.lrqad@deped.gov.ph * blr.lrpd@deped.gov.ph

Leave a Reply

Your email address will not be published. Required fields are marked *

For students and teachers

Looking for a school?

Look up the enrollment, teachers, classrooms and facilities of more than 60,000 schools across the Philippines, from DepEd’s public data. Free to use.

Philippine Schools Directory by TeacherPH · every region, province, division and district